Risk Register

Assessment date: 2026-07-13

Verified Defects

ID Finding Evidence Impact Next action
VD-001 First-boot web credential behavior is documented inconsistently. include/config.h says first-boot AP forces password change; src/web_server.cpp serves /wifi behind current credentials and does not enforce a first-boot password change. Operators may deploy with default admin/admin longer than intended. Design an explicit credential-onboarding flow in a separate security task.
VD-002 Requirements.md referenced payload schema v3 while code, README, and tests use schema v4. payload_codec.cpp uses kSchema = 4; test_payload_codec validates schema v4 vectors. Contract documentation could mislead future protocol work. Updated schema references to v4 in this harness task.
VD-003 docs/TESTS.md referenced old lilygo-t3... environments. Current platformio.ini has production, debug, and test. Developers could run non-existent verification commands. Replaced with current compile-only and on-device commands.
VD-004 PlatformIO static analysis currently fails outside repository-owned firmware logic. Default pio check -e production --fail-on-defect=high fails when cppcheck reaches toolchain-xtensa-esp32/.../bits/c++config.h:520; --skip-packages avoids that header but still reports high defects under .pio/libdeps/production/ArduinoJson/.../Variant/ConverterImpl.hpp. The canonical verification command is strict and correctly returns non-zero until analyzer scope/policy is explicitly decided. Resolve in a separate tooling task; do not silently add skips, suppressions, or dependency changes just to obtain a passing check.

Probable Risks

ID Finding Evidence Impact Next action
PR-001 Direct lib_deps are version-ranged, not exact. platformio.ini uses ^ ranges. New installs may resolve different library versions. Apply exact pins in a separate dependency-only commit after review.
PR-002 PlatformIO Core version is not locked by the repository. Local pio --version is 6.1.18; CI installs the expected version but local shells may differ. Local and CI behavior can drift. Keep expected core version documented and update only in a dedicated tooling task.
PR-003 Static analysis coverage depends on PlatformIO's available check tools. pio check is available, but tool availability can vary by runner cache/network. CI may fail for tool setup rather than firmware defects. Keep output visible; add pinned analyzer packages only if needed later.
PR-004 .vscode/extensions.json had pre-existing local modifications. git status --short reported it modified before this task. Review may mix user-local editor changes with harness work if committed together. Keep it out of this task unless the user explicitly asks.

Missing Tests

ID Gap Existing partial coverage Next action
MT-001 No native host test environment yet. Transport logic is close to pure logic but still includes Arduino.h. Follow staged extraction plan in docs/engineering/test-matrix.md.
MT-002 ACK sender-side validation is not directly unit-tested as production code. Some ACK-related behavior is documented and indirectly covered by compile checks. Extract ACK parse/validation into a small pure helper, then add native or embedded tests.
MT-003 Retry timeout calculation is not directly unit-tested. Sender stats and constants exist; behavior is runtime-coupled. Extract timeout calculation before adding tests.
MT-004 SD history parser is not covered by a dedicated test suite. Web input and CSV contracts are documented; compile checks cover buildability. Extract current/legacy CSV line parsing to a pure helper.
MT-005 Web POST validation is not covered beyond helper sanitizers. test_html_escape covers escaping, URL encoding, and device ID sanitization. Add focused tests when web parsing is extracted.

Missing Documentation

ID Gap Next action
MD-001 No measured hardware power baseline is recorded in this branch. Record current, light-sleep-off, and light-sleep-on measurements in a separate HIL/power task.
MD-002 No Gitea runner inventory is recorded. Document runner labels and container prerequisites in CI operations notes once the runner exists.
MD-003 No sanitized HIL local config example exists yet. Add hil_tests/config.example.yaml when pytest harness scaffolding starts.

Security Decisions

ID Current decision Status Recommendation
SD-001 AP password default is changeme123. Confirmed. Replace with per-device provisioning in a separate approved task.
SD-002 Web defaults are admin/admin. Confirmed. Add forced first-boot credential change in a separate approved task.
SD-003 Credentials are stored in Preferences. Confirmed. Assess NVS encryption, flash encryption, and credential rotation separately.
SD-004 LoRa packets are not cryptographically authenticated. Confirmed. Design message authentication and replay handling separately; preserve current wire contract until approved.
SD-005 Replay protection is limited to batch IDs, duplicate tracking, sender IDs, and ACK rate limiting. Confirmed. Add explicit threat model before changing protocol.
SD-006 OTA, firmware signing, secure boot, and flash encryption are not configured in this project. Confirmed by source/config search; hardware fuse state unknown. Decide production boot-chain policy in a separate security task.

Hardware-Dependent Questions

ID Question Why it matters Proposed verification
HQ-001 Does GPIO14 role selection remain stable with SD SCK reuse on receiver boot? main.cpp releases the role pin before SD uses GPIO14. HIL boot-role and SD mount tests.
HQ-002 Does chunked light sleep preserve 1 Hz meter UART capture on real meters? Power behavior depends on UART timing and FreeRTOS scheduling. Sender HIL with smart-meter UART simulator and real meter.
HQ-003 Are ACK windows sufficient at worst-case RSSI/SNR and duplicate retries? LoRa airtime and receiver delay depend on RF environment. Paired-board RF soak tests with ACK loss injection.
HQ-004 Is SD logging reliable across missing, full, and corrupt cards? Runtime currently treats SD as optional but history depends on it. HIL SD fault injection.
HQ-005 Are heap and stack margins acceptable during web history queries and long LoRa batches? ESP32 memory pressure is hardware/runtime dependent. Long-duration HIL with heap/stack telemetry.